Project Information
Location Abu Dhabi - Reem Island
Client Bunya developer / Koora sports
Contractor ASAS group
Year of Completion 2023
Project Brief

Playground construction has civil and MEP activities. It includes excavation, leveling, compaction, grass laying, drainage structure, kerb stone, fencing with foundation. MEP works – Installation of high mast high lumen light includes erection of pole, cable laying, electrical works.

Project Description
Development of football ground for Koora sports to provide training, conduct tournaments etc. This project includes parking, refreshment area, changing room, locker, advertising hoardings.
Challenges & Solutions
Summer heat in construction causes health risks, material issues, equipment overheating, productivity loss, and requires adjusted schedules and cooling strategies.